# 🏗️ Israel fast-tracks data centres to become an AI superpower, but its power grid pushes back

AI Today · published 2026-11-28T07:50:00Z · https://ai-today.com/news/27cbe156-4781-43ca-9227-72befcbe1f75?lang=en

![Aerial view of the port of Ashdod](https://img.ai-today.com/d/a69fd3604aa54ab49dae5dea6839d0f5/LZb_BKtokuyuwMjkdJeP9ISE7SQDZba8bIaMxFzqhmY.jpg)

- 🏗️ Israel classifies AI data centres as national infrastructure to bypass local planning rules.
- ⚡ Flagship: the Ofek Data Center near Ashdod, 130 MW rising to 200 MW, initially costing $1.5bn.
- 🔌 The brake: requests for about 27 GW of grid connections; the electricity regulator caps new centres at 200 MW.
- 🌍 Experts see geopolitical aims behind it, including military advantage and bargaining power.

🏗️ Israel wants to become a "global AI superpower", as Prime Minister Benjamin Netanyahu said in June, and is clearing hurdles for new data centres to get there. Since February, AI data centres count as national infrastructure so that planning and building rules can be bypassed. Within five years the country is to be the third AI power, Netanyahu said in September. [Al Jazeera](https://www.aljazeera.com/) lays out the drive in an analysis. The flagship is the Ofek Data Center north of the port of Ashdod. Financed by a consortium led by US operator [Serverfarm](https://www.serverfarmllc.com/) and the Israel Infrastructure Fund, it is to cost $1.5bn at first, with another $5bn planned for upgrades. It is to open with 130 MW, grow to 200 MW, run Nvidia GPUs, connect to Europe by undersea cable and be finished in the second half of 2029. ⚡ The bottleneck is electricity. Grid operator Noga received connection requests for about 27 GW, according to the trade outlet DCD, several times the country's average consumption. The electricity regulator therefore wants to cap new data centres at 200 MW and demand guarantees of 2 million shekels per megawatt. Experts see strategy rather than returns behind the build-out: control over computing power, faster AI at home and military advantage.

🔗 **Nvidia as the anchor.** Israel's place in AI is closely tied to Nvidia. The chipmaker bought Israeli networking specialist Mellanox in April 2020 for nearly $7bn. The networking business built on it brought in more than $21bn in the third quarter of 2026, about 18 percent of quarterly revenue, Al Jazeera reports. Israel is Nvidia's largest research site outside the US: headcount has doubled in three years to 6,000 across seven development centres, and a campus for up to 10,000 people is planned in Kiryat Tivon near Haifa. Chief executive Jensen Huang calls Israel a "second home".

⚡ **Where the power is to come from.** According to Israeli media reports, the Ofek centre is to be fed directly by an 850 MW gas-fired power station next to Ashdod's port. Energy Minister Eli Cohen is also counting on nuclear energy and on natural gas from the Tamar, Leviathan and Karish fields in the eastern Mediterranean, near maritime borders disputed with Lebanon; a fourth field, Katlan, is due to start producing in 2027. Israel currently has 67 data centres, according to the directory Data Center Map.

🔌 **Why the regulator is braking.** DCD traces the flood of connection requests to the law that declared data centres national infrastructure. Noga froze the processing of requests for centres of 8 MW or more in July, a pause expected to last until early December. Besides the 200 MW cap per new centre, data centres are to be disconnectable at times of peak load. At the same time the regulator plans to allocate an extra 1 GW to large data centres, lifting the sector's contracted capacity to more than 3 GW, about a fifth of the consumption expected for 2030. A final decision was due after a three-week consultation, DCD reported.

🧭 **Strategy, not returns.** "Fast-tracking permits is a governance decision," London-based AI adviser Rajiv Dalal told Al Jazeera; securing the electricity to run what gets built is a question of whether it can be done. Israel is small, grid-constrained and dependent on imported hardware, he said, while superpower status needs gigawatt-level capacity and steady access to chips. Mark Esposito of Harvard's Berkman Klein Center calls domestic data centres "the territorial anchor of AI power": they draw in cloud providers, AI labs and suppliers, and countries with their own infrastructure will hold bargaining power over those without. Mark Muro of the Brookings Institution points to fast, stable local inference as an advantage for business, the grid and the military. Israel has already used AI militarily in Gaza and the West Bank. Netanyahu justified the course in February with national security: "We must do this because we are a small and threatened country."

🇪🇺 **What it means for Europe.** Europe lags in data-centre construction because of grid bottlenecks, slow permits and public opposition. Shifting computing loads abroad, possibly to Ofek too, brings flexibility. Keeping data inside the EU costs a premium of 30 percent or more by European Commission estimates but shields it from foreign access, Bertin Martens of the Brussels think tank Bruegel stresses. Economist Simone Vannuccini of Université Côte d'Azur warns that relying on Israeli computing power could make Europe politically quieter: "Maybe we will be less prone to criticising something."

## Sources

- [How Israel is fast-tracking data centres in bid to become 'AI superpower'](https://www.aljazeera.com/news/2026/11/28/how-israel-is-fast-tracking-data-centres-in-bid-to-become-ai-superpower)