# 🛰️ AI data centres in orbit: a JPL scientist shows what their economics hinge on

AI Today · published 2026-11-25T06:30:00Z · https://ai-today.com/news/520a2ba3-faf9-4335-9d81-d25cdbddb81b?lang=en

![Solar arrays and radiators of the International Space Station](https://img.ai-today.com/d/eaddb8a6a4c140f7b42adbb990bdab72/M76raUsspcKtl1sVGzFBg5eRkZYrJGXl-429X9q7OIQ.jpg)

- 🛰️ Slava Turyshev of NASA's JPL finds hard physical and economic limits for orbital AI data centres.
- 📐 For 1 megawatt, the base case needs about 5,640 m² of solar panels and 2,500 m² of radiators.
- 💶 Launch and build together could cost only $250–1,000 per kilogram.
- 📄 It is one analysis, a preprint on arXiv submitted in April 2026.

🛰️ Data centres in orbit are meant to live on near-constant sunlight. Slava Turyshev of NASA's [Jet Propulsion Laboratory](https://www.jpl.nasa.gov) argues that sunlight alone does not decide the case: power generation, heat rejection, the data link to the ground, utilization and lifetime all have to work at once. His preprint on arXiv, submitted in April 2026, estimates about 5,640 m² of solar panels and 2,500 m² of radiators for 1 megawatt of computing power. 💶 In his model, launch and satellite manufacturing together could cost only $250 to $1,000 per kilogram to compete with ground facilities. The Falcon 9 launch price he uses as a benchmark is, on its own, 3.4 to 13.5 times above that allowance. He names processing data in space and edge computing on communications satellites as credible early uses.

📰 The work is getting attention now through a [Universe Today report](https://www.universetoday.com/articles/the-physics-wall-facing-orbital-ai-data-centers) of November 25. According to that report, the US Federal Communications Commission approved the application of [SpaceX](https://www.spacex.com) the same day to launch one million "Starmind" orbital data centres by 2040, and Google booked a flight on a Blue Origin rocket earlier in November to test its Project Suncatcher concept. The study itself is older than both.

📐 **Mass.** In the [paper's base case](https://arxiv.org/search/?query=Turyshev+orbital+data+centers&searchtype=all), photovoltaics, energy storage and radiators alone come to 29.4 kilograms per kilowatt. Adding the fixed mass of the spacecraft raises that to 34 to 59 kilograms per kilowatt, or 34 to 59 tonnes for 1 megawatt. The panel area refers to the beginning of the system's life, in an orbit with a lot of sunlight.

💶 **The price test.** Turyshev takes $10,000 to $40,000 per kilowatt as the benchmark for infrastructure on the ground. At roughly 40 kilograms per kilowatt, that produces the narrow ceiling for launch and manufacturing. Communications, operations, utilization and lifetime penalties are not yet counted in it. Universe Today puts the current price of a dedicated Falcon 9 launch to low Earth orbit at about $3,360 per kilogram.

📡 **Data and radiation.** According to Universe Today, optical links to the ground may peak at 200 gigabits per second but realistically sustain about 13 to 26, because they need a line of sight to a ground station and cannot pass through clouds. Radiation adds to this: cosmic rays flip bits in memory, error correction eats computing time, and over a five-year mission radiation and micrometeoroids wear down electronics and solar panels.

🔭 **When it could pay off.** For general computing serving users on the ground, the abstract says the case closes only if little data has to travel to and from Earth, the hardware is heavily used and lasts a long time, and launch plus manufacturing become very cheap. A nearer option is, for example, analysing Earth-observation data in space and sending down only the results.

🔧 **Maintenance.** A second paper, submitted in August 2026, models operations. For a 1-megawatt cluster of ten active 100-kilowatt nodes plus one reserve node, it arrives at 393 to 419 standardized operations per megawatt and year, with 5.3 to 9.0 tonnes of resupply. Planned refreshes outnumber replacements for random failures. The reference design for a first deployment is uncrewed and maintained by robots; dedicated personnel only come into play at several hundred megawatts up to gigawatts.

⚖️ All of these figures are model results under stated assumptions, not measurements from a facility in space. Both texts are preprints, and no peer review is indicated there.

## Sources

- [S. G. Turyshev: Orbital Data Centers (two preprints, April and August 2026)](https://arxiv.org/search/?query=Turyshev+orbital+data+centers&searchtype=all)
- [The Physics Wall Facing Orbital AI Data Centers](https://www.universetoday.com/articles/the-physics-wall-facing-orbital-ai-data-centers)

---
This post was selected, researched, written and rated by AI. The AI can be wrong: check the sources.