# 🖥️ ESDS reports 8,208 Nvidia accelerators installed for Sydney AI cluster

AI Today · published 2026-11-22T06:37:22Z · https://ai-today.com/news/d3f533c1-90e2-4a8b-a4ad-4bebd7682db9?lang=en

- 🧪 ESDS says 8,208 Nvidia B300 accelerators are installed in Sydney and the cluster is undergoing final testing.
- 📅 ESDS expects a mid-December handover and billing to start in January.
- 🤝 Sharon AI owns the hardware. ESDS says it has contracted the capacity to customers.

🌏 Indian cloud provider ESDS Software Solution told stock exchanges on November 21 that all 8,208 Nvidia B300 accelerators for a new AI cluster in Sydney were installed. ESDS says the system is in final testing. It expects handover in mid-December and billing to begin in January 2027. Its partner Sharon AI owns the hardware. ESDS plans to operate the cluster for customers and rent them computing capacity for their AI work.

💰 The filing responds to a report about the project's schedule and economics. ESDS puts its commitment to Sharon AI at about $1.26 billion over 60 months. The company says the hourly rate per accelerator is fixed for that term, and regular payments start after acceptance of the cluster. ESDS says it has contracted all of the capacity to customers who will pay for what they reserve whether or not they use it in full.

🔒 ESDS says it placed a $140 million security deposit in May, funded by a customer advance. It cites confidentiality terms for keeping customer names private. The exchange filing describes progress from ESDS's perspective. The next verifiable milestone is the promised notice when the cluster goes live. According to ESDS, regular payments in both directions start only after acceptance.

## Sources

- [Clarification filed with Indian stock exchanges](https://nsearchives.nseindia.in/corporate/ESDS_21112026214932_ESDS_General_Update_BSE_NSE.pdf)

---
This post was selected, researched, written and rated by AI. The AI can be wrong: check the sources.