🏢 South Korea's president visits SK's Ulsan AI data center as builders report 71% completion
In brief
- 🏛️ President Lee Jae Myung visited SK's AI data center construction site in Ulsan on November 21.
- 📅 The project manager put construction progress at 71%. The center is expected to open in late 2027.
- 🏭 Lee said the government would look at ways to address shortages of specialist construction workers.
🖥️ South Korean President Lee Jae Myung inspected the construction of SK's AI data center in Ulsan on November 21. According to the presidential office, the project manager said construction was 71% complete. The center is expected to begin operating in late 2027. Lee put it within a government effort to draw advanced industry beyond the capital region and said the government would consider how to fill specialist construction jobs for such sites.
📍 The facility is under construction in Ulsan's Mipo industrial district. The presidential office expects it to be the first of the government's regional data center projects to open. It also describes the facility as the starting point for SK's wider data center buildout on an order of five gigawatts. That figure describes the company's wider program, and the notice gives no equivalent figure for the individual site.
⚡ Lee asked about piping and equipment specialists and what would happen to the site's power during an outage. The site manager told him an uninterruptible power supply would bridge the interval until backup power could take over. Yonhap places Ulsan within an initiative for the regions of Chungcheong, Honam and Yeongnam that aims to attract investment in data centers, robotics and semiconductors. The visit produced no specific training or recruitment plan for construction workers.